How we generally build a new patio:
- Dig down, apply hardcore
- Lay the concrete slab
- Leave a flat finish for patio slab / tiles to be laid
This job can take between 1-4 weeks depending on size, clearing and specific customer requirements.
How we generally approach an extension:
- Dig down for footings
- Lay foundations
- Underground brickwork to d.p.c
- New brickwork built to current building regulations
- Windows/doors built in
- Roof cut & tiled and all lead work done
- Decorate inside to customer’s requirements