Kitchens and Bathrooms

How we generally fit a new kitchen:

  • Strip out existing kitchen
  • Put down new flooring if required
  • Plumb in sink & get water back on!
  • Fit base units
  • Fit bridging units
  • Fit oven and other accessories

These jobs take approximately 1-2 weeks depending on size and finish ie. tiling etc.

How we generally fit a new bathroom:

  • Strip out old bathroom
  • Remove old tiles
  • Replaster whole room
  • Put new floor down
  • Fit the new suite on-top (rather than cutting around it)
  • Tile & Grout

These jobs take approximately 1 week, depending on size & finish.